The Grantham Rail Trail will be undergoing some pavement repairs this week.
Rankin Construction Inc. is tentatively scheduled to start the work on July 9, 2024. Repairs will be made to the sections between Ridgeview Ave. and Carlton St.; Linwell Rd. and Tecumseh St. (parallel Clover St.); plus Atherton Ave. and Tecumseh St.
The repair process will include two days of asphalt pavement removals and granular base repairs, as well as two days of asphalt paving.
Some temporary trail closures will be required to protect construction workers and complete the work safely and cost-effectively, but every effort will be made to minimize inconvenience to both residents and trail users.
If you require more information, please contact:
Jim Stranges, C.E.T.
Project Supervisor
City of St. Catharines
905.688.5601 ext. 1606